Statement of Compliance checklist (Victorian subdivisions)
Everything that has to be true before the SoC application is lodged, in the order it usually falls over. Pair it with permit to Statement of Compliance for the phases behind it.
Project / stage
Permit no.
Target SoC date
1. Permit conditions
Work from the permit condition register, not from memory.
- Every condition with a "before Statement of Compliance" trigger is Discharged with evidence filed — or formally Not applicable with the reason recorded.
- Conditions requiring an agreement (Section 173, maintenance, WSUD) are executed AND registered on title where the condition says so, with the dealing number in the register.
- Endorsed plans on file match the as-constructed works; any secondary consent or plan amendment is approved, not just lodged.
- Conditions owned by referral authorities have that authority’s written confirmation, not council’s assumption of it.
2. Council engineering
- Practical Completion (or the council’s equivalent acceptance) issued for every stage the SoC covers, with the defects list closed or formally deferred to the maintenance period.
- As-constructed drawings, asset data and any digital asset register submitted in the council’s required format and acknowledged.
- Maintenance / defects-liability security lodged in the required form and amount; the register records the expiry and return dates.
- Supervision, inspection and any outstanding council fees paid, with receipts filed against the condition they satisfy.
- Street naming, lighting, signage and landscaping obligations that gate SoC are complete or formally bonded where the council allows it.
3. Referral authorities
Each authority issues its own consent; the SoC application needs all of them.
- Water retailer: works accepted, fees and contributions paid, consent to Statement of Compliance issued.
- Melbourne Water (or the relevant drainage authority): drainage scheme fees settled, works accepted, consent issued.
- Electricity distributor: works complete, easements in the agreed form, consent or clearance letter issued.
- Telecommunications: provider confirmation that the development is serviced or the agreed arrangement is in place.
- Gas (where reticulated): works complete and clearance issued.
- Any other referral authority named on the permit (DTP, CFA, catchment authority) has issued its consent.
4. Plan of subdivision and title
- The certified plan matches the constructed lots, reserves, roads and easements; every easement created by an authority consent is shown correctly.
- For staged subdivisions, the register states what THIS stage still owes without double-counting an earlier stage’s discharge or borrowing a later stage’s works.
- Public open space, reserves and road vesting are as the permit and the plan require.
- SPEAR lodgement pack complete: application, certified plan, every authority consent, council engineering sign-off.
5. Lodge once, not twice
- Lodge the SoC application only when every consent is in hand — a partial application restarts the clock and the conversations.
- The register shows who is chasing any last consent and the date it was promised.
- Client and purchaser-settlement teams have the realistic SoC date, not the hopeful one.
6. After SoC (the file is not closed)
- Defects liability / maintenance period start and end dates recorded, with the inspection booked before expiry.
- Security return dates and the release request path recorded per authority.
- As-constructed and asset handover obligations that fall after SoC are in the programme with an owner.
- Bond and security release requests drafted against the conditions they close out.